The movement on the bypass of Krasnoyarsk was completely discovered


September 2 16:30
At the round of Krasnoyarsk, where the overhaul of the site from 1 to 5 km continues – from the Drokinsky mountain to the overpass through Kotelnikov Avenue – they opened the movement for cars in all four lanes. This was reported today in Cruitor.
It is noted that on the left side, in the direction from the Drokinsky mountain to the city – they have already completed the main amount of work, it remains to lay the upper layer of asphalt concrete coating, install lighting and complete the arrangement.
On the right side completed the dismantling of a road fence, milling of the existing asphalt concrete, the device of the base and the lower layer of the coating, disassembling and layout of the soda; Work is underway to remove the soil-lowering layer, cutting cuvettes and repairing culverts.
On the site, a system is also mounted for the collection and discharge of water from the carriageway; In the water protection zone of Kachi, 20 treatment facilities are equipped – water intakes with filter material; The cuettes and slopes of the embankment are strengthened using a geogrid; Install lighting, put in order stopping with the device of transition-speed and dividing strips; mount the barrier fence; Signs and markings will also be upheld, noise stripes will be applied.
Recall that the repair of Krasnoyarsk bypass began in April of this year and since then the traffic was carried out in one lane in each direction.
“Now technical readiness is 75 %. It is planned to fully complete the overhaul of the facility before the end of September, ”Krudor said.
Note, bypass of Krasnoyarsk is one of the most loaded areas of agglomeration. In recent years, the intensity of traffic there is about 37 thousand cars per day, by 2033 it should approximately increase to 60 thousand in knocks, and in 2041 – reach 76 thousand cars per day.