Krasnoyarsk residents were told when the long -awaited pool in the northern


The multifunctional complex with the pool under construction in Krasnoyarsk at the intersection of streets on May 9 and Vodopyanova is 95 %ready. The contractor reported this to the deputy head of the city – the head of the Department of Urban Planning Sergey Shikunov.
Materials on the topic
Now workers are eliminating the customer’s comments, setting up ventilation systems and pools, and are also preparing to send water samples for examination. The finishing work came to the finish line, the arrangement of furniture is underway.
Outside the complex, improvement ends: put the paving stones, asphalt parking with 66 seats, plants trees and shrubs.
Recall that under the contract, the contractor had to complete the complex by April 30, but in The strength of a number of circumstances of the work dragged on.
“This is a technically complex object, it was necessary to link everything. The equipment here is the most modern, domestic. In a room with pools, we showed the initiative, decided to decorate it. They invited the designer here, he looked, connected the Soviet and modern periods. It turned out 2 bright panels. They will delight visitors, ”said Andrei Astapov, director of the construction of Kamenchik LLC.
The capacity of the complex will be 268 people per shift. There are three floors in the building: on the first there is a wardrobe, cafe, two lockers – male and female, two hammams, shower, rooms with two pools – a children and an adult (the depth of the first 0.8 meters, the second – 3.5 meters). On the remaining floors-a children's room, a gym for strength training, a sports museum, administrative premises, it is planned to open a checker-shahmati club.
The object should be completely ready by the end of AugustAfter it, the commission of the construction and housing control service in the Krasnoyarsk Territory will check it and it will be commissioned.
“We expect that in November the pool will accept its first visitors. Everyone will be able to come here, including it is adapted for people with limited mobility, for example, for them we have provided separate showers, they will not meet any restrictions, ”said Sergey Shikunov, head of the Department of Urban Planning.
Recall that the multifunctional complex is built at the expense of the city budget. PDinking it will be transferred to the Balance to the Main Directorate for Physical Culture, Sports and Tourism.