In Krasnoyarsk from 1June 4 in the area of ​​the cultural and historical center on the arrow Power engineers will begin repairing the pipeline. The road pThey will not overlap it with omnity, but the drivers are waiting for restrictions.

So, on Dubrovinsky Street, the driveway will be narrowed to one strip in each direction, and on Karl Marx (from the Armo pedestrian bridge to the intersection with Karatanov) – up to two lanes.

It is planned to complete the work on July 25.

The highway in this section is very old, it is already over 20 years old. To ensure reliable heat supply to residents, the pipeline must be completely replaced, ”said SGK. – For the specified period, we will update the network of a network with a length of 150 m, with a diameter of 500 mm and carry out major overhaul of the heat chamber“.