Other

Nazarovo power engineers are preparing for the heating season 2026–2027 / Society news of Krasnoyarsk and the Krasnoyarsk Territory / Newslab.Ru

30 March 17:08

Preparations for the upcoming heating season of 2026–2027 have begun at Nazarovskaya GRES. This year, the total investment of the Siberian Generating Company (SGK) in the repair and investment program of the station will amount to 3.1 billion rubles.

In accordance with the requirements of the Ministry of Energy of the Russian Federation, the enterprise has developed a comprehensive plan of organizational and technical measures. Traditionally, the key stage of preparation includes hydraulic tests, which are scheduled in Nazarovo in May and late summer. After the completion of the heating season, tests are necessary to identify hidden defects in heating networks: in the summer, specialists eliminate them and carry out scheduled repair work, including replacing pipelines in problem areas.

Just before the start of the new heating season, the networks will undergo a pressure control test, which will identify additional or hidden damage in order to eliminate them before supplying heat to consumers.

In 2026, power engineers will replace 2.5 km of heating networks. Two sections of the heating main will be repaired directly during the heating season – thanks to the temporary pipeline technology, shutting off the heat supply to residential buildings and social facilities will not be necessary. Summer repair work will take place in the area of ​​the City Court, as well as at the address: Karl Marx Street, 44. In these areas, last year, diagnostics using a specialized robotic complex revealed defects that required a complete replacement of the heating main.

According to the General Director of Nazarovskaya State District Power Plant, Dmitry Morozov, scheduled repair work is planned here in July. “The section of the heating network in the central part of the city provides heat to a significant part of the city – the 8th and 10th microdistricts, as well as the sector from Karl Marx Street to the villages of Gornyak and Mekhanizatsiya. In addition, socially significant facilities are located here: schools, kindergartens and healthcare institutions. Therefore, it is important to complete all the work that began here 2 years ago,” the station manager emphasized.

It is worth noting that in this microdistrict, power engineers have already completely replaced the networks in three areas: in the area of ​​\u200b\u200bthe street. Chulymskaya (590 m), in the area of ​​the Victoria store (450 m), as well as in the area of ​​the children's clinic (500 m).

Work to replace networks is also planned in the village of Bor, in the area of ​​the hospital campus on Chernyakhovsky Street, 2 and 4, where important social infrastructure facilities are also located.

Related materials

In addition to the repair campaign, the plan of preparations for the new heating season includes emergency training that will take place in the spring and autumn. During these exercises, power engineers will work out cooperation in eliminating conditional accidents in the heat supply system with the involvement of operational services of the city administration, the headquarters of civil defense and emergency situations, the Unified Duty Dispatch Service, as well as enterprises of the industrial hub.

The main confirmation of the full implementation of all planned measures will be the receipt of a passport of readiness for the heating period. Let us note that last year Nazarovo successfully received this document, and last winter passed without any accidents: even during the period of abnormally low temperatures in January, power engineers provided reliable heat and electricity supply to city residents.



















Related links:

  • In 2026, SGK will carry out work at 60 objects of the heat supply system in Kansk




Ashley Davis

I’m Ashley Davis as an editor, I’m committed to upholding the highest standards of integrity and accuracy in every piece we publish. My work is driven by curiosity, a passion for truth, and a belief that journalism plays a crucial role in shaping public discourse. I strive to tell stories that not only inform but also inspire action and conversation.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button