In Krasnoyarsk, resource men put in order the streets after earthwork

June 20 15:16
In Krasnoyarsk, enterprises continue in active mode to close previously issued orders for the repair of underground utilities. This was told in the city hall.
Today, June 20, the intermediate results of the events were discussed at the meeting, which was held by the acting head of the city Alexei Shuvalov. The working meeting was attended by heads of structural divisions of the city hall, district administrations and resource -supplying organizations.
So, SGK restored the improvement in almost 90 territories: road sections were paved, pedestrian zones and lawns were equipped. The General Director of the Yenisei TGK Oleg Bubnovsky said that all territories where the utilities carried out excavation work would be returned to the former appearance.
“The repair campaign on the heating networks last year dragged on until deep autumn. It is simply impossible to perform large volumes of transfer in a short summer, so we “owe” in some areas with the implementation of the improvement. In general, in recent years, we have been able to seriously improve the condition of the main heating networks, the calm heating season is confirmed, ”said Oleg Bubnovsky.
Recall that in the current season, as part of its repair program, SGK plans to repair and update pipelines on 80 sections of heat -power outlets with a length of about 54 km. From the beginning of this year, 344 orders have closed the “paint”, another 143 places of disclosure are in work.
“This summer we pay special attention to the places where the work was carried out earlier, but for various reasons, impaired improvement was not restored. In total, this year we plan to close more than 1000 orders issued by the enterprise for the repair of engineering communications, ”said Oleg Goncherov, general director of Krak.
Also, the improvement in 157 plots was restored by PJSC Rosseti Siberia. According to acting The director of the Rosseti Siberia branch – Krasnoyarskenergo Sergey Chernyavsky, first of all, the energy sectors paid attention to the central part of the city.
“In the central and railway areas, 120 orders have been completed and closed at the moment. Additionally, the city has restored the improvement of 46 more orders who are preparing to close, ”said Sergey Chernyavsky.
It should be noted that since the beginning of the year, resource -supplying organizations have closed about 600 orders, having restored landscaping in the plots, this is almost three times higher than the indicators of the same period of 2024.
The acting head of the city, Alexei Shuvalov, drew the attention of participants in the meeting to the need to comply with the schedules of the closure of orders and maintain a high rate of work.