In 2026, five road facilities will be reconstructed in the Krasnoyarsk Territory

January 23 17:30
In 2026, five road facilities in the Krasnoyarsk Territory will be put in order as part of the national project “Infrastructure for Life”. This was reported by the regional Department of Highways.
Thus, on the Yeniseisk-Vysokogorsky highway, the construction of a new bridge over the Rudikovka River and approaches to it will be completed. The crossing is planned to be completed this summer.
In parallel with this, work will begin on the bypass of Krasnoyarsk, in the area of the transport interchange near the village of Solontsy.
“Currently the contractor is reconstructing communications at the site. This season it is planned to install new turning loops and an overpass. In addition, the contractor will begin construction of an underground pedestrian crossing. It is planned to complete this work, as well as lay a new asphalt concrete pavement, install a barrier fence, and electric lighting by the end of 2027,” said Andrey Zhuravlev, head of the Krasnoyarsk Territory Highway Administration.
.jpg)
The reconstruction of the Krasnoyarsk-Kuznetsovo-Zykovo road will also continue, in the section from the crossing to the village of Zykovo and along the railway track. Road workers will move communications, build a roadbed, and also build detours for installing culverts. The contractor must commission the facility by 2027.
In addition, this year it is planned to commission bridges across the Seiba and Srednyaya Seiba rivers on the Sayany highway. Specialists have already equipped bypass roads and started constructing supports. Both structures should be ready by November.
Let us remind you that in 2026, as part of the national project, repairs will be carried out at 59 objects of the regional road network. In total, it is planned to restore 168 km of road surfaces and put into operation 250 linear meters of bridges.
Newslab now in MAX. News is also published in OK | VK | Zen | Telegram
Related links:
- In the Krasnoyarsk Territory, two-thirds of road projects in 2026 have been contracted
- Road workers put in order the second section of the Yeniseisk – Vysokogorsky highway