Finishing work has begun at a Krasnoyarsk school that closed 6 years ago

April 23 12:00
In Krasnoyarsk at a school on the street. Finishing work has begun on the airport terminal. This was reported on the social networks of the City Hall “GradVestnik”.
Now in the building, specialists are plastering the walls, pouring screed on the floor on the second and third floors, installing electrical wiring, installing radiators, and replacing windows.
“Previously, all emergency partitions, floors, doors and side porches, and the old roof were dismantled in the building. The latter was completely updated, and the floor slabs, foundation and load-bearing structures of the building were strengthened. The builders replaced 41 windows out of 220 and filled 1,700 sq. m of floor and plastered 5200 sq. m of walls on the first floor. Screeded surfaces of 1000 sq. m on the 2nd and 3rd floors,” the urban planning department clarified.
The next stage is laying porcelain stoneware slabs, arranging bathrooms, finishing the facade, replacing the remaining windows, landscaping the area, installing an individual heating point, painting walls and ceilings, installing all doors, installing a ventilation system and a security alarm system.
Let us remind you that the school is on the street. Aerovokzalnaya, 4g in Krasnoyarsk was closed in 2020 due to emergency conditions. The major renovation of the facility is being carried out by the StroyInnovatsiya group of companies, at its own expense, within the framework of an agreement on the comprehensive development of the territory on the street. Partisan Zheleznyak. The work should be completed in 2027.