S19 Rzeszów Południe – Babica. The TBM penetrated the first aisle of the tunnel

Tunnel under the Grochowicz Hill will be 2,255 m long and will consist of two aisles, connected by 15 transverse passages and an emergency passage. Each aisle will accommodate two traffic lanes, an emergency lane and safety bands.
The rest of the article below the video:
The use of the TBM “Karpatka” machine, provided by the Spanish company Acciona Construccion in cooperation with Mostostal Warszawa, allows the investment to be carried out in difficult geological conditions.
The TBM machine has impressive parameters: 114 m long, 15 m wide and weighs 4,400 tons. Its hydraulic-electric drive, 12 engines with a total power of 12 MW and 471 cutting tools allow for effective tunnel drilling at a depth exceeding 100 m.
Expressway and tunnel. Technological and geological challenges TBM shield after penetration – northern portal, tunnel in section S19 Rzeszów Południe – Babica.
It was originally assumed that drilling one nave would take about 10 months, but complicated geological and hydrological conditions, as well as the detection of methane in July 2023, extended the process.
During the drilling of the first nave, approximately 950,000 tons of excavated material, 23 thousand were used MWh of electricity and over 11,000 housing elements. The production of the elements took place on site, in the prefabrication hall in Lutoryż, where the Passenger Service Area (MOP Lutoryż) will ultimately be built.
See also: Germany praises the Polish megaproject. A revolution in traveling to the Baltic Sea
Tunnel on S19. Via Carpatia – strategic transport corridor
After completing the first aisle, preparations for the rotation of the TBM machine began, which is expected to take approximately three months. This process requires inspection, service and possible repairs of the device. Additionally, modifications to the machine are planned to improve its operation when drilling the second nave.
See also: Technological breakthrough. This is supposed to be the deepest tunnel in the world [WIDEO]
Completion of the construction of the tunnel, which is a key element of the Via Carpatia route, is planned for January 2028. The current overall progress of the works is approximately 57%.
The S19 expressway is part of the international Via Carpatia route connecting Northern and Southern Europe. In Poland, the route will be approximately 700 km long.
Source: GDDKiA Rzeszów