In Krasnoyarsk, the repair of five retaining structures on the streets of Mashinostroiteli and Tymoshenkov ended. This was reported in the city road department.

Materials on the topic

On the street of Mashinostroiterators near the house No. 21, workers dismantled the dangerous sections of the old wall, strengthened it with a monolithic concrete bandage, arranged a drainage system, and then plastered and painted. At the house No. 19, the old concrete blocks were replaced by modern gabions – structures made of mesh filled with stones, which effectively strengthen the soil massif.

On Tymoshenkova Street, work at three facilities is also completed. In houses No. 78 and 78a and on the site between them, the old structures from the blocks were replaced with new monolithic walls, for the construction of which the reinforcing frame was mounted and concrete was poured.

In the meantime, the repair of other retaining walls in the city is nearing completion. On the streets of Kirensky, 25 and Kuibyshev, 85 work were performed by 85 %. At Kirensky, workers are changing the dangerous structure that could collapse and install a new fence. It remains to complete the finishing work on the new monolithic wall on Kuibyshev and restore the improvement.

The work continues on Sayanskaya Street, where the retaining wall is located along residential buildings No. 247-249 and heating mains. The contractor strengthened the structure and is preparing to replace emergency sites. It is planned to complete the repair of this facility before the end of September.

In total, this year in Krasnoyarsk, according to the plan, 11 retaining structures will be put in order.