In Krasnoyarsk, at the construction site near the railway station, the assembly of the Valentine's tunneling complex began. This was reported today in the official public subway.
Specialists have already mounted a stationary shield and nine technological carts.
Video from the construction site
With the help of the Valentine TPMK, the left distillation tunnel will be built between the station “Stzalnaya” and “Kopylova Street”. In parallel on the right distilled tunnel, the Anastasia TPMK will work after it completes the penetration from the “Revolution Square” to the “station”.
Recall that the first two metro tunnels in Krasnoyarsk began to be built in the fall of 2024. Mechanized shields – “Solomey” and “Catherine” – laid the tunnels around the clock, which will connect stations on the streets of Shakhters and Karl Marx. The first passed 1705 meters, the second – 1963 meters.