Video a less known express road, but that will be ready in July. What does it look like now / “An important stump like a whole highway”

A new section of express road that few people have heard will be ready in July, according to HotNews.ro sources, although a few months ago the Minister of Transport announced as a deadline for inauguration. Once open to traffic, the section will decongest a city in Transylvania and will make the drivers access to Cluj-Napoca much easier.
The express road DEX4 A3 – Tureni/DN1 will be ready to open traffic in July, sources close to the project said for HotNews.ro.
The new term comes after in March the Minister of Transport, Sorin Grindeanu, announced that the piece of road will be ready on May 17, although independent observers were talking as “the most optimistic scenario”.
Removes traffic from Turda and facilitates access to Cluj-Napoca
The new high -speed road, about five kilometers long, will connect the Transilvania A3 highway and the national road DN1, near Tureni.
Although it is a short section, it will be part of a larger project, DEX 4 Turda-Dej, and the piece is now close to completion will have the main purpose to remove much of the A3-DN1 transit traffic to Cluj-Napoca, from Turda.
Because the Transilvania A3 highway reaches Gilău, far west of Cluj-Napoca, most drivers who want to reach the Transylvanian metropolis choose to get off A3 on DN1 before Turda and cross the city to reach Cluj.
The new express road will eliminate the transit of Turda municipality and will allow the traffic in the direction of Cluj-Napoca closer to the city.
VIDEO – What DEX4 express road now looks like
“A stump like a highway”
“It is a stump as important as a whole highway,” he appreciated for HotNews.ro Ionuț Ciurea from the Pro Infrastructure Association, one of the organizations in the civil society that monitor the big infrastructure projects in the country.
About this project, the Pro Infrastructure Association (API) said that it is expected “with the soul at the mouth of Cluj, by those in the pass, but also by the inhabitants of the most swearing city in the area, Turda”.
“A year ago, at the beginning of 2024, we hoped that the Dimex-Con association would make a beautiful figure and to inaugurate the lot in December 2024, 2 months before the contractual term, February 2025. Unfortunately, since summer 2024 it was clear that this was no longer possible, and even that the contractual term will be exceeded,” explained Pro Infrastructure.
“It is their first major project and the relief is difficult. It is always very difficult for relatively small companies, which have only done [drumuri] County and buildings, to pass from the lower divisions in Liga 1: Other money – we are talking about another cashflow, this is the big problem, another pressure, another technical major ”, considers the expert.
The piece of express road has a length of only 5 km, but it involves making two connection roads with A3 and DN1 whose connection straps – some with two lanes per direction – also measure another 5 km. Plus many structures, how short the road is, and many considerable consolidations – support walls, explains Ciurea.
Of construction, from September 2023, the association of DIMEX 2000 (leader)-Autotehnorom-OPR Asphalt-Oras Publicas y Regadios-con-a. The value of the project is 562 million lei, and the physical stage has exceeded 89%.
The contractual deadline was 18 months from September 21, 2023, the date of issuing the start order. According to Centralization Cestrin the date of completion was initially February 17, 2025, but then the deadline was officially extended until May 17, 2025.

The express road DEX4 A3 – DN1 (Tureni)