Krasnoyarsk road workers responded to criticism about the repair of Dubrovinsky Street

May 7 10:50
After a series of negative assessments from the Krasnoyarski, the quality of repair of Dubrovinsky Street in the Zheleznodorozhny district, specialists Sudab said that the work is performed using technology and There are no complaints about the contractor yet.
Materials on the topic
Recall that the inhabitants noticed that the recently laid lower layer of asphalt “was already swelling near the hatches” and suggested that The upper layer will hide these shortcomings, which is why the road will quickly become unusable.
In surprise they said that this would not happen:
“In order for the hatches to be on a flush with the upper layer of the coating of the carriageway, the alignment layer of the road surface is always performed first, then areas are cut off to raise the plates of ceilings of the wells to the required mark. Then the upper layer of asphalt concrete is already performed. Such is the repair technology that asphalt is even. Now, on Dubrovinsky Street, work is underway to lay the aligning layer of asphalt, after which the workers will begin to replace the plates of wells. And all the bumps visible now in the places of wells will be eliminated. ”
Krasnoyarstsev also assured that each stage of the work is controlled from different sides: curators of surprise and road laboratory assistants.
“If the quality does not comply with the current standards, such work is not accepted or paid. And the contractor must eliminate the identified shortcomings. At this stage, there are no complaints about the contracting organization, ”the department said.
Links on the topic:
- “Traffic jams cannot be avoided”: in the center of Krasnoyarsk they control the movement due to the overlap of Dubrovinsky
- Krasnoyarka has been asking for Basayskaya Street (video) since last year