In a school under construction in Krasnoyarsk at the intersection of Elena Stasova and Chernyshev streets, the building frame has begun to be assembled, the city hall’s telegram channel “GradVestnik” reported.
The contractor is reinforcing the floor of the basement floor of the 4th block and installing columns. After pouring the monolithic slab, installation of the floor will begin.
Excavation work and installation of a pile field for the remaining blocks are also ongoing. Three tower cranes are installed on the site.
At the school on Elena Stasova Street, the building frame began to be assembled
Let us remind you that the school is designed for 1280 places and will consist of four blocks and a warm passage. In addition to classrooms, the project includes a large assembly hall, a sports block with rooms for gymnastics, choreography and fitness aerobics, a dining room with 625 seats, a library, a conference room, a photo and film studio, carpentry and home economics workshops.
“The non-standard format of the site and the features of the relief determined the architectural solution: the blocks will be of different heights, and the landscaping of the territory will be multi-level. The school will be completed in 2028,” the mayor’s office said.
Newslab now in MAX. News is also published in OK | VK | Zen | Telegram
Related links:
- Façade finishing has begun at a school under construction in Krasnoyarsk's Tikhye Zoryi
- In Krasnoyarsk Michurinsky, the school under construction is 58% ready