The territory of the future school in the Oktyabrsky district of Krasnoyarsk began to be fenced off


January 27 10:51
In Krasnoyarsk, at the intersection of Elena Stasova and Chernyshev streets, they began to gradually prepare a site for the construction of a school.
As reported in the TG channel of the city hall “GradVestnik”, bThe concrete fence appeared on the side of Elena Stasova.
“The contractor, JSC Firm Kultbytstroy, needs to install a fence, organize a camp for specialists, remove external utility networks, and also construct a pit for piling work. One of the features of the future construction of the school will be the construction of retaining walls – there are three local ones and one system at the site. This is due to the features of the terrain,” explained the mayor’s office.
Let us remind you that the construction of a school for 1280 students will begin this year. It is planned to open on September 1, 2028.