On September 15, the terms of four contracts for road repair are completed in Krasnoyarsk


September 5, 18:40

In Krasnoyarsk, streets repair came to the finish line. The city hall reminded that four municipal contracts are completed on September 15.

Contractors need to have time to finish work on the streets of Metallurgov, Shumyatsky, Suvorov, travel along the park of the 400th anniversary of Krasnoyarsk and Solnechny Boulevard.

“If the repair of these sites is not completed on time, then the contractors are threatened with penalties for each day of delay. The rest of the contracts still have time until October 15, all objects of 2025 should be prepared for this date, ”the city hall recalled.

The press service noted that this year the customer service with the administrations of the districts drew up a schedule for each facility. This was necessary so that the contractor would start repairing at a new facility after completing work at the previous one. Thus, the city hall planned to optimize the work of the contractors and prevent the time.

“The terms, quality and completeness of the work performed by the customer’s service help to monitor public controllers from among active citizens. If desired, any indifferent resident can participate in regular inspection raids and in the acceptance of objects. To become a public controller is simple. To do this, contact the local branch of the Public Front, ”the press service recalled.

The city hall noted that the townspeople show great interest in the topic of road repairs. Since the beginning of this year, more than 2 thousand appeals related to the quality and safety of the road network have received the municipal customer. More than 95% of them, users received answers, the rest of the questions are in the study. Many streets and road sections are updated precisely in response to the requests of the Krasnoyarsk residents.

In Krasnoyarsk, with the support of the national project “Infrastructure for Life”, taking into account the wishes of residents this year, 40 objects are put in order, of which 12 are in their work, 26 completed and 2 more are planned for production.