Due to de-energization, a transport collapse occurred in the capital. Local authorities reported a temporary stop of local metro and trams, as well as a delay in the movement of railway transport.
Soon, the work of urban electric vehicles resumed.
🔴🇨🇿 Alerte Info – une panne massive d'électricité a toché plusieurs régions de tchéquie ce jeudi, paralysant trams, métro, Distributeurs et ascenseurs. Un DysfonctionNement au Post électrique de Chodov Serit en case.#Tchéquie #PRAGUE
pic.twitter.com/1SGCN2C54K
– Media Express (@Media_Express_e) July 4, 2025
Massive Power Outage Hitting Prague and Large Parts of Bohemia. In the City, Trams and Metros Not Running, Many Emergency Calls FOR PEOPLE Stuck in Elevators.
Millions are Affected. How Quickly The System Can Collapse Without Precious Energy. pic.twitter.com/t3hht6ydjf
– Peter Spina ⚒ Goldseek | Silverseek (@goldseek) July 4, 2025
Firefighters on social networks X reported approximately 215 challenges associated with people stuck in elevators. They had to be evacuated.
V Souvislosti s rozsáhlým výpadkem elektřiny řešíme prozatím 215 záchran z vhange.
– Hasičskutch záchranný sbor čr (@hasici_cr) July 4, 2025
Due to the disconnection of electricity, reserve generators were connected in Czech hospitals, the US Minister of Health Personal Valek said on social networks. According to him, nothing threatens the patients, but some medical interventions had to be transferred for a while.
K Aktuálnímu Rozsáhlému výpadku Elektrické Energie.
Chci Všekhny Uklidnit. Zdravotnická zařízení mají pro tyto situace připravené jasně dané postupy. V nemocnicích zasažených výpadkem nabíhly záložní agregáty. Péče o Pacienty Není ohrožena. Samozřejmy může dojít k odkladu …
– Vlastimil válek (@vlvalek) July 4, 2025
The government called the disconnection of a “serious and destructive situation” and created the central crisis headquarters, informed Radio Prague International. According to the Czech operator of the čeps transmission system, the power outage was caused by the technical malfunction, namely the cliff of the phase wire of the high -voltage line (V411), as a result of which eight large substations partially refused.
The police said that there is no data so far that a large -scale power outage is terrorist or cyber attack.
V Souvislosti s výpadkem proudu jsme zvýšili hlídkovou činnost na zasažených územích a naši kolegové a kolegyně řídí doopravu na vybraných křižovatkách v zasažených místech. Bližší informace zjištujeme.
– policie čr (@policiecz) July 4, 2025