In Krasnoyarsk, the collapsing shore of the island of Tatyshev will strengthen for 80 million rubles

May 29 9:11

The administration of Krasnoyarsk began searching for a contractor to strengthen the coast on the island of Tatyshev. The initial cost of the lot is almost 80 million rubles.

We are talking about a small segment of the coastline – 315 meters. Its maximum height is 6 meters. The site is located next to the October Bridge on the north side of the island.





Coastal, should be made of torn career stone of rocky rocks, resistant to frost.

Also, the winner of the tender will need to dismantle the stairs that leads to the water. Now she is in disrepair, the passage to her is closed.

“The main task of the contractor is to stop the destruction of the coast. We are engaged in these works in advance. Under the terms of the contract, experts should go to the site at the end of June. Just by this time, excavations will be completed by archaeologists-this is an obligatory part of the work, since the shore of the island enters the boundaries of the identified object of the archaeological heritage “Krasnoyarsk. Settlement of the island of Tatyshev-2”, ”said Sergey Shikunov, head of the department of urban planning.

After all the events, the contractor will have to restore the impaired state of aquatic biological resources in the Yenisei and the reproduction of the young: to release sturgeon, nelma, taimen, karius, siga or sterlet into the river.

The work is scheduled for two years – until the end of August 2026.