The wish of a Maramureş for the authorities: “The steps of your mothers be the same as our holidays”

A Maramureş community lives a Easter nightmare, due to the 108A County Road restoration works, on the Salsig – Benessed portion. Every night is a nightmare, people say. The Maramureș County Council claims that: “This discomfort is temporary but necessary”.

“They destroyed the road and left,” says a local. Photo: Doru Șupere

“I have a wish for the politicians from the Maramureș County Council and the” specialists “from the Maramureș County Roads: The pastures of your mothers should be as happy and quiet as our holidays, of the people from Sălig. For a few days, we are hundreds of people in the village, every 3 hours.”, Said the well -known HR specialist, Doru Șupere.

He posted a film with the nightmare, in which he says that portions of road were very good. “We have a piece of the road of Sălig in which the road was very good, asphalt, everything was fine, it was quiet, the people who lived here, including my family could sleep quietly.”

Ever since the rehabilitation works began, for several weeks, all the asphalt has been scraped and no speed limiters have been placed, no traffic lights have been introduced, he adds: “They have destroyed the road for a few weeks and left it. “

“When the trucks, tanks and cars, in speed, through our houses on DJ108A are passing, the noise is hell, the windows tremble, the walls of the houses crack and you feel that you move not with bed, but with a house.“He says.

The situation is no more enjoyable the day when, he says, “It is hard to be able to stay in the yard, because you cannot breathe from the dust clouds that the vehicles pass through the houses. The clothes put to dry in the yard are blackened in a few minutes, and the windows and curtains for the holidays already have two dust fingers in a few days. ”

“They destroyed the whole road and they disappeared, they took their Easter leave.”

Ship claims that after destroying the road, the workers took holiday leave:

“The imbecils who are made to work on the repair of the road have destroyed the whole road, which looks like Ukraine after bombing and have disappeared, have taken Easter leave since Wednesday, beating the citizens living here, whose lives and holidays are not important for these politicians.”

The work of restoring the county road 108A, on the Salsig – Benesat portion is “A sinister gambling to thousands of people in Maramureș. I tell and show you in this video all that happens for a few weeks: citizens, houses, holidays and lives are the last things that the nonsensics take into account which, with the asphalt on the road, have scraped any trace of quality standard,” he concluded a hat.

CJ Maramureș sent pictures that would show that on Thursday he worked on the road. Photo: cj mm

CJ Maramureș sent pictures that would show that on Thursday he worked on the road. Photo: cj mm

The reaction of the County Council

“Adevărul” asked for a point of view of the Maramureș County Council regarding the stage of the works on DJ 108A Gârdani – Benesat.

The works are executed by the road insert SA based on a contract worth 55 million lei, financed through the National Investment Program “Anghel Saligny”, and aims to completely rehabilitate a section of 15.38 km that includes:

– Modernization of the carriageway,

– the arrangement of the streams and bridges,

– Construction of sidewalks and bus stations,

– Rehabilitation of side access and four bridges – it is shown in response.

According to the entrepreneur, the works were not stopped on Wednesday, April 17, but continued in the Cheile Ţicăului area until Thursday afternoon, around 5:00 pm. In support of this statement, the entrepreneur has made available images attesting to the activity in the field. The works will be resumed on Tuesday, according to the assumed execution chart. The deadline remains the fall of 2025”, States CJ.

During the entire duration of the works, the responsibility regarding the state of the road – including the signaling, snow removal and maintenance – belongs exclusively to the performer, based on the contractual provisions, is shown in response. So the Maramureș County Roads Company has no attribution in terms of the state of the road.

“We understand the discomfort generated by the works in progress, especially in the decommissioned areas and apologize to all citizens and traffic participants. This discomfort is temporary but necessary, and our goal is that, at the end of the project, we offer to the communities in the modern and safe road infrastructure,” support the officials from the County Council.

In response, it is more art that, at the request of the entrepreneur, between March 15 and June 15, 2025, traffic restrictions are established for vehicles with a mass greater than 7.5 tonnes, between kilometers 81+487 and 96+868, except for public transport and local economic activities.

“The Maramureș County Council will continue to monitor the works closely and maintain a constant dialogue with all the parties involved, in order to respect the terms and quality standards.”is shown in response.

Ashley Davis

I’m Ashley Davis as an editor, I’m committed to upholding the highest standards of integrity and accuracy in every piece we publish. My work is driven by curiosity, a passion for truth, and a belief that journalism plays a crucial role in shaping public discourse. I strive to tell stories that not only inform but also inspire action and conversation.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button