The project and construction of the Youth Palace on the Fundamental Square was estimated at 5 billion rubles

August 25 15:33
In Krasnoyarsk, they completed the choice of a contractor who will take up the design and construction of the Youth Palace on the Patchic Square. Information about this appeared on the public procurement website.
Only one company participated in the purchase. Its name has not yet been published. It is she who was recognized as the winner. She proposed to reduce the initial price of 5.199 billion rubles to 5.147 billion rubles.
Judging by the draft contract, the Youth Palace in Krasnoyarsk will consist of two buildings. In the first, 4-story “House of Youth“a transformed concert hall, several conference halls and places for training, an exhibition gallery, an observatory with a telescope, a cafe, etc. will be located. The interior project must comply with the concept of a corporate removal style. Nearby they plan to place the Patriot Park for the rest of children and youth, as well as to improve the territory.

The second building will also have 4 floors, And it will be divided into 4 sections.
“Basic premises: Media, Big Data, Bio, Auto, Alternative Energy, Information Technologies, Industrial Design, Material Science and Nanotechnology, Industrial and Applied Robotics, Virtual, Automated and Mixed Aviation Systems, Apisten Cosmonautics “,” Applied Mathematics “,” Haytek-Tsekh “and other premises, entrance zones, specialized landfill, garage, hotel type and meals“, – It is indicated in the draft contract.
Preparatory work on the project should be completed by December 2026, the construction should be completed by May 2028, and put into operation from June to October 2028.
We will remind, earlier on the ancestral square planned to be built The complex of buildings of the Krasnoyarsk choreographic college and the modern International Center for creative industries “Pozdeev Center”. For their creation, an international architectural competition was announced, and after the development of detailed projects, a construction contract has already been concluded. But then they were terminated, citing the fact that the conclusion of a contract with the only supplier contradicts the requirements of the law.