Hot water is being returned to four districts of Krasnoyarsk

June 5 9:42
In Krasnoyarsk, on June 5, 10-day hydraulic tests were completed along the circuit of CHPP-2, which includes Oktyabrsky, Zheleznodorozhny, Bolshaya Sverdlovsk and Central districts.
According to the SGK, 818 km of pipelines have been inspected, and the identified weak points have already been eliminated or included in the summer repair program.
“Since yesterday we have been filling the system. After the parameters are brought up to standard, From the middle of today we will begin supplying hot water to residents. Notifications about the need to complete repair work on intra-house networks and open shut-off valves have already been sent to housing organizations,” the energy workers said.
Related materials
The next check of communications will take place from June 15 to 24 along the contour of the Krasnoyarsk CHPP-1. It includes Leninsky, Kirovsky and part of the Sverdlovsk region, including the Yuzhny Bereg and Vodniki microdistricts.
Residents are asked to take into account that this year the boundaries of the heat supply circuits of the thermal power plant are slightly different; they are markedand the interactive map of the SGC.
Related links:
- Krasnoyarsk residents can ask questions by phone about the quality of hot water and the timing of its shutdown
- Deputy: in Krasnoyarsk it is possible to halve the duration of hot water shutdowns