In Krasnoyarsk, on a long -suffering interchange through the northern highway, the sidewalk is destroyed

August 21 6:34
In Krasnoyarsk, the sidewalk began to collapse on a car interchange over the North Highway. Experts revealed numerous coating disorders and significant soil failures under the sidewalk and the carriageway near the support No. 6.
Materials on the topic
As I.O. The head of the capital construction department Alexander Paramygin, the monitoring of the denouement is constantly carried out, and the first defects were revealed in July, which was indicated by the contractor – Siberian company:
“He did not eliminate them, the failures have increased, so now they sent a repeated demand until August 25 to eliminate the identified violations of the integrity of the coating. According to the municipal contract, the contractor must perform these works at his own expense. ”
Recall The road that connects a take-off to the Solonets-2 microdistrictThe inhabitants were waiting for several years. It should have been handed over in 2024, but Siberian delayed the construction timeTherefore, the city hall terminated the contract with him. The issue of the volume and quality of the work performed is now being decided in court, the denouement itself has not yet been put into operation.
Links on the topic: