Rosseti Siberia eliminated all damage to energy facilities in the main network after a hurricane in the Krasnoyarsk Territory

April 8 22:28

Rosseti Siberia experts eliminated all technological violations on power facilities in the main network of 6-110 kV (provides mainly power supply to settlements) after a stormy front, held from April 5 to 6 in the Krasnoyarsk Territory.

The recovery work involved 175 brigades, including from Kuzbass, Tomsk, Tovy and Altai: 428 power engineers and 199 special equipment.

Currently, experts are working out individual consumer applications in a 0.4 kV network (provides power supply directly to residential buildings). The main causes of power supply disorders are damage to networks, on which a hurricane wind brought up third -party objects (elements of roofs, fences, facades) and excess wind load.

Materials on the topic

Recall that the main blow of the elements with gusts of wind of more than 32 meters per second fell on the western, southern, eastern and southeastern territories of the region. The main forces of the power engineers were concentrated in the eastern and southeastern zone-Nizhnegashsky, Rybinsk, Irbean, Uyarsian regions, which were the last to strike the elements. The branch of Krasnoyarskenergo worked in a special mode, the elimination of the consequences of the storm was under the control of the Rosseti Siberia operational headquarters.

Power engineers are in constant interaction with the regional department of the Ministry of Emergencies of Russia, ODDS and executive authorities.

If the power supply in the house does not appear, call the Rosseti contact center by phone:
8-800-220-0-220, The call in Russia is free (short number – 220) or write the exact address in Telegram: @ivan_rossetisib.